Municipal Rooftop Installations

Stara Kamienica PS obtained project financing for these installations in the amount of 85% of eligible costs from the Regional Operational Program of the Lower Silesian Voivodship. As a substitute investor, Stara Kamienica PS is responsible for the contractor selection process, project supervision and acquisition of funding.

3 installations with a total of 206 photovoltaic panels (total capacity of 58,71kW) were installed and commissioned in late December of 2018. These installations include: Primary School in Stara Kamienica, Sewage Treatment Plant in Stara Kamienica, Municipal Kindergarten in Stara Kamienica.

The total value of the project: PLN 421.775,68 zł
Financing amount: 357.822,95 zł

Stara Kamienica PS, as the member of the Izerski Renewable Energy Cluster, plans to implement many more renewable energy projects in the upcoming years, both in the Stara Kamienica Municipality as well as in other municipalities within the Renewable Energy Cluster.